IRP 2 FCP ক্লিনিং কাজ সম্পন্য হয়









IRP 2 FCP ক্লিনিং কাজ সম্পন্য হয়









Observation: DTW 107 Radio Communication checking complete. This DTWs communication is very bad.1. In DTW 107, We checked up to 10 minutes. In…
IRP#01 Main substation, Electrical Panel Room, OGR Electrical Panel Room Cleaning & Visual Check Work Completed.
1.1 NOS new Camera installing 2.UTP Cable Change 3. Connector Chang
Dtw-220 & 219 RTU, VFD & CCTV Panel all equipment cleaning