    Instrumentation Findings of Month (July,2022)

    Posted onJuly 27, 2022September 4, 2022

    SL/NO PROBLEMS TAG LOCATION REMARK 1 When the pump runs, the pump Motor + MOV runs together.  Which does not follow the normal…

    Listen to the Message Instrumentation Findings of Month (July,2022)Continue

  • MONTHLY REPORTS

    IRP-1 & 2 all DTW CCTV UPS maintenance, replace & install

    Posted onJuly 27, 2022August 14, 2022

    Savar-Keraniganj Well Field Plant IRP-1 & 2 all DTW’s  CCTV UPS maintenance , replace & install SL No. DTW No. Problem Activity Comment…

    Listen to the Message IRP-1 & 2 all DTW CCTV UPS maintenance, replace & installContinue

  • DAILY REPORTS

    DTW101 CCTV UPS installation

    Posted onJuly 26, 2022July 27, 2022

    Listen to the Message DTW101 CCTV UPS installationContinue

  • REPORTS

    Report: IRP-2 Dome Camera and Panel preventive maintenance.

    Posted onJuly 5, 2022July 5, 2022

    Equipment Status Dome Camera: All Ok Power Supply: Ok Ring Switch: Ok Findings: After raining water found in panel. Suggestion: Solution for water…

    Listen to the Message Report: IRP-2 Dome Camera and Panel preventive maintenance.Continue

  • REPORTS

    Report: IRP-1 Electrical Room RTU Panel Preventive Maintenance.

    Posted onJuly 5, 2022July 5, 2022

    Cleaning Status: Completed. Findings: No problem found.

    Listen to the Message Report: IRP-1 Electrical Room RTU Panel Preventive Maintenance.Continue

  • REPORTS

    Report: IRP-1 OGR Electrical Room RTU Panel Preventive Maintenance.

    Posted onJuly 5, 2022July 5, 2022

    Cleaning Status: Completed. Findings: No problem found.

    Listen to the Message Report: IRP-1 OGR Electrical Room RTU Panel Preventive Maintenance.Continue

  • REPORTS

    Report: IRP-2 Sub-station CCTV Server Panel Preventive Maintenance.

    Posted onJuly 5, 2022July 5, 2022

    Device Status OLT : OK UPS: OK ONU: Ok POE Switch : OK Findings: Too much dust inside all device. Suggestion: New separate…

    Listen to the Message Report: IRP-2 Sub-station CCTV Server Panel Preventive Maintenance.Continue

  • REPORTS

    IRP-1 DTW (101 to123) SCADAPACK, TRIO JR,LIT & PIT REPORT.

    Posted onJuly 5, 2022July 5, 2022

    DTW SCADAPACK TRIO JR LIT PIT COMMENTS 101 OK OK OK OK 102 OK OK NOT OK OK 103 OK OK OK OK…

    Listen to the Message IRP-1 DTW (101 to123) SCADAPACK, TRIO JR,LIT & PIT REPORT.Continue

  • REPORTS

    IRP-1 All DTW NEV Voltage Report

    Posted onJuly 4, 2022July 5, 2022

    NEV voltage [Report] SL No. Location Voltage Comments 01. DTW-101 37mV 02. DTW-102 170mV 03. DTW-103 231mV 04. DTW-104 1.1V 05. DTW-105 42mV…

    Listen to the Message IRP-1 All DTW NEV Voltage ReportContinue

  • REPORTS

    DTW UVR, ELD, GiMAC , ACB & LV Panel P/M of Month [Report]

    Posted onJuly 4, 2022July 5, 2022

    SL No. DTW No UVR ELD GiMAC ACB Comments 01. 101 02. 102 03. 103 04. 104 05. 105 06. 106 07. 107…

    Listen to the Message DTW UVR, ELD, GiMAC , ACB & LV Panel P/M of Month [Report]Continue

Page navigation

Previous PagePrevious 1 … 17 18 19 20 Next PageNext

Dhaka Water Supply and Sewerage Authority

+88 01797187749

Join With Us

© 2026 TEAM ICE

  • Home
  • ICE LAB
  • Product Specifications
  • Technical Papers