  • IRP-1 backwash holding tank (2P01A) pump Checking & Problem Found.
    ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez

    IRP-1 backwash holding tank (2P01A) pump Checking & Problem Found.

    Posted onSeptember 10, 2022September 10, 2022

    problem found: IRP-1 Backwash holding tank -A pump’s cable terminal box gets short circuit & burn. For instance, a fault signal came in…

    Listen to the Message IRP-1 backwash holding tank (2P01A) pump Checking & Problem Found.Continue

  • DTW115 SCADA PACK INSTALL COMPLETE
    ACTIVITY | DAILY REPORTS | DTW | Jewel | Pappu | Parvez

    DTW115 SCADA PACK INSTALL COMPLETE

    Posted onSeptember 8, 2022September 9, 2022

    Listen to the Message DTW115 SCADA PACK INSTALL COMPLETEContinue

  • Optical Fiber restoration work at DTW103
    ACTIVITY | CCTV | DTW103 | Jewel | NETWORK CONNECTIVITY | Pappu | Parvez

    Optical Fiber restoration work at DTW103

    Posted onSeptember 7, 2022September 24, 2022

    In the time of Civil work the contractor’s people cuts down the fiber cable to conduct their civil work. As a result this…

    Listen to the Message Optical Fiber restoration work at DTW103Continue

  • OGR Booster pump (E) checking complete.
    ACTIVITY | DAILY REPORTS | Jewel | MOV | Pappu | Parvez

    OGR Booster pump (E) checking complete.

    Posted onSeptember 7, 2022September 7, 2022

    Problem: When the pump is stopped and normally shuts off, a fault automatically occurs in the MOV (4P01-E).  In this case the valve…

    Listen to the Message OGR Booster pump (E) checking complete.Continue

  • OGR Booster Pump supply fan (4M02B) checking and findings.
    ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez

    OGR Booster Pump supply fan (4M02B) checking and findings.

    Posted onSeptember 6, 2022September 6, 2022

    Listen to the Message OGR Booster Pump supply fan (4M02B) checking and findings.Continue

  • ACTIVITY | CCTV | DTW | Jewel

    CCTV PANEL, UPS, POE SWITCH, ONU CLEANING COMPLETE DTW-208 .

    Posted onSeptember 6, 2022September 6, 2022

    Listen to the Message CCTV PANEL, UPS, POE SWITCH, ONU CLEANING COMPLETE DTW-208 .Continue

  • DTW-208 RTU PANEL, VFD CLEANING & CHECKING COMPLETE.
    ACTIVITY | DTW | MONTHLY REPORTS | Pappu

    DTW-208 RTU PANEL, VFD CLEANING & CHECKING COMPLETE.

    Posted onSeptember 6, 2022September 6, 2022

    Listen to the Message DTW-208 RTU PANEL, VFD CLEANING & CHECKING COMPLETE.Continue

  • MONTHLY REPORTS

    Electrical Team Monthly work plan(September-22)

    Posted onSeptember 6, 2022September 6, 2022

    Sl No. Date Location Task Name Work update Remarks 2 9/3/2022 33 KV interlink HT Network visual checking & Monthly tree trimming work….

    Listen to the Message Electrical Team Monthly work plan(September-22)Continue

  • ACTIVITY | CCTV | DTW | Jewel | MONTHLY REPORTS

    CCTV PANEL, UPS, POE SWITCH, ONU CLEANING COMPLETE DTW-203 .

    Posted onSeptember 5, 2022September 6, 2022

    Listen to the Message CCTV PANEL, UPS, POE SWITCH, ONU CLEANING COMPLETE DTW-203 .Continue

  • ACTIVITY | DTW | MONTHLY REPORTS | Pappu

    DTW-203 RTU, VFD CLEANING & CHECKING COMPLETE.

    Posted onSeptember 5, 2022September 6, 2022

    Listen to the Message DTW-203 RTU, VFD CLEANING & CHECKING COMPLETE.Continue

Page navigation

Previous PagePrevious 1 … 15 16 17 18 19 20 Next PageNext

Dhaka Water Supply and Sewerage Authority

+88 01797187749

Join With Us

© 2026 TEAM ICE

  • Home
  • ICE LAB
  • Product Specifications
  • Technical Papers