ACTIVITY | DAILY REPORTS | Jewel | Pappu | Parvez | Pending Issue IRP-1 to IRP-2 SCADA controlling communication antenna Arrangement work complete. Posted onSeptember 29, 2022October 12, 2022
ACTIVITY | DTW | Parvez Level Sensor Report 2022 Posted onAugust 30, 2022November 14, 2022 Level Sensor Report October 2022 SL NO. DTW NO. STATIC LEVEL PUMPING LEVEL Type STATUS 01 101 5.8 ❎Level Sensor problem. 02…
ACTIVITY | DAILY REPORTS | DTW | Jewel | Parvez | REPORTS DTW #120,121,122 VFD , RTU AND CCTV PANEL CLEANING Posted onNovember 27, 2022November 27, 2022 DTW #120,121,122 VFD , RTU AND CCTV PANEL CLEANING COMPLETE
ACTIVITY | CCTV | DTW | Jewel | MONTHLY REPORTS CCTV PANEL, UPS, POE SWITCH, ONU CLEANING COMPLETE DTW-203 . Posted onSeptember 5, 2022September 6, 2022
ACTIVITY Field Pump Checking & Maintenance. Posted onDecember 3, 2023December 3, 2023 Checking and maintenance of 2 field pumps completed.
ACTIVITY | Parvez PWID106: IRP-1 All FCP & LOP panel clean. Posted onNovember 21, 2023November 21, 2023