Device Status
OLT : OK
UPS: OK
ONU: Ok
POE Switch : OK
Findings: Too much dust inside all device.
Suggestion: New separate panel Installation for OLT device.
Device Status
OLT : OK
UPS: OK
ONU: Ok
POE Switch : OK
Findings: Too much dust inside all device.
Suggestion: New separate panel Installation for OLT device.
Dtw-220 & 219 RTU, VFD & CCTV Panel all equipment cleaning
Daily Work Plan October 2022🠗 SL/NO Date PROBLEMS TYPE LOCATION REMARK 1 01.10.2022 DTW-105 CCTV checking maintenance. COR CCTV Team ICE: ✅PAPPU, Parvez,…
Problem: Shutdown time is ACB not open.Problem found: ACB Internal control unit not working found.Observation: DTW 203 UVR checked, When plug PTT UVR…
1 new camera installation 2. UTP cable change 3. Connector change 4. IP Setting 5. IP Seating