DTW-102 Scada Pack Programing And Install Done




DTW-102 Scada Pack Programing And Install Done




1. connector change 2. IP Setup
DTW-221,217,123 Modbus communication Problem DTW-221 & 217 new serial communication cable install DTW- 123 VFD controller and Modbus serial communication cable check Done….
1.Cable connector change 2. IP Setup
Installation and Commissioning of the vacuum circuit breaker is relatively simple, and it is a process that must be completed before leaving the…
Observation: Radio communication checking complete DTW 221.1. In DTW 221, We checked up to 10 minutes. RSSI Value (Dc volts) MAX: 2.700V, MIN:…